Because of the problems and delays, the Bush road will remain closed this afternoon until 3:00 PM in the direction from Sint Bernard Bridge to Zagersgut Road.
Furthermore, due to the delay in the planned work,onThursday March 11, 2010 from 8:00 PM until Friday March 12 at 6:00 AM—the Bush road remained closed to allow the work to continue.
The Sector of R.O.B., department of maintenance, Traffic Police of St. Maarten and NV GEBE informs the general public that Bush Road will be completely closed on 10th of March, 2010 starting at 8p.m. in the evening throughout the night until 6a.m.on Thursday 11th of March, 2010. Only residents of the Bush Road will be allowed to enter during the above-mentioned time.
During this timeframe, General contractor Windward Roads Infrastructure will be laying the new High Tension cables in the trenches alongside the Bush Road, from the entrance of Blijden Drive until the Prins Bernard Bridge.
Due to the needed workspace, the temporary bridges accessing the properties over the open trench will be removed in order to lay these cables.
Residents living along the Bush Road needing to use their transportation during this time frame are urged to park their vehicles on the other side of the road.
During this timeframe, residents will not be able to access their property with this vehicles.
Full access to the properties will be restored at 6.00am on Thursday morning.
This small inconvenience will allow us to execute the necessary upgrading of the Utilities on the Bush Road.
During this project, Windward Roads will accommodate the residents anyway as possible.
The Sector of ROB, N.V. GEBE and Contractor Windward Roads apologizes for any inconveniences this may cause.
For more information regarding the above-mentioned work, interested persons can contact the Sector of R.O.B. department of New Project Development and infrastructural Management (Mr. C.A. Buncamper or Mr. B. Ortega) or NV GEBE Maintenance and Execution Department.